EARTH - CONCRETE - MASONRY WORKS | |
CONCRETE EXCLUDING STEEL (PER M3) |
USD |
Labor & material | 130 |
Labor only | 30 |
EXCAVATION (PER M3) | |
Sandy soil | 4.5 |
Semi-rocky soil | 5.5 |
Rocky terrain | 7.5 |
* All Prices Exclude VAT | |
Prices as of October 2007 | |