SITE WORKS |
Description |
USD |
I- Excavation & Clearing |
|
1- General excavation of normal soil including hauling away
and dumping of material to municipality-approved pits (in m³) |
8-9 |
2- General excavation of rock including hauling away and
dumping of material to municipality-approved pits using explosives (not
exceeding 1 m depth) (in m³) |
10-11 |
3-Trench excavation for Sewage network, Piping depth between ( 0
- 2 m ), width between ( 0.6 - 1 m) |
12-13 |
4- Clearing of site in soft to medium hard ground including
hauling away and dumping of material to municipality-approved pits (in m²) |
9-10 |
|
|
II- Filling & Backfilling (all in m³) |
|
5- Backfilling with approved excavated materials stored on
site around foundations including watering and compaction (in layers not
exceeding 300mm depth) |
8-9 |
|
|
III- Shoring (all in m²) |
|
6- Diaphragm wall for watertight excavation including
excavation, tie-back system and dewatering, 600mm thick |
450-500 |
7- Ditto, 800mm thick |
500-550 |
8-Interspaced pile wall with shotcrete for dry excavation
including excavation and tie-back system |
350-400 |
9-Secant pile wall for watertight excavation including
excavation, tie-back system and dewatering |
425-475 |
|
|
IV- Foundation Piling (Drilling only) |
|
10-Micro piles, using hydraulic piling machinery, 150-250mm
diameter (per linear meter of piles) in normal soil |
25-35 |
11-Bored piles, using hydraulic piling machinery, 500-600mm
diameter (per linear meter of piles) in normal soil |
40-50 |
|
|
Excluding
VAT |
|
Last
updated February 2019 |
|
|
|