| SITE WORKS | |
| Description | USD |
| I- Excavation & Clearing | |
| 1- General excavation of normal soil including hauling away and dumping of material to municipality-approved pits (in m³) | 8-9 |
| 2- General excavation of rock including hauling away and dumping of material to municipality-approved pits using explosives (not exceeding 1 m depth) (in m³) | 10-11 |
| 3-Trench excavation for Sewage network, Piping depth between ( 0 - 2 m ), width between ( 0.6 - 1 m) | 12-13 |
| 4- Clearing of site in soft to medium hard ground including hauling away and dumping of material to municipality-approved pits (in m²) | 9-10 |
| II- Filling & Backfilling (all in m³) | |
| 5- Backfilling with approved excavated materials stored on site around foundations including watering and compaction (in layers not exceeding 300mm depth) | 8-9 |
| III- Shoring (all in m²) | |
| 6- Diaphragm wall for watertight excavation including excavation, tie-back system and dewatering, 600mm thick | 450-500 |
| 7- Ditto, 800mm thick | 500-550 |
| 8-Interspaced pile wall with shotcrete for dry excavation including excavation and tie-back system | 350-400 |
| 9-Secant pile wall for watertight excavation including excavation, tie-back system and dewatering | 425-475 |
| IV- Foundation Piling (Drilling only) | |
| 10-Micro piles, using hydraulic piling machinery, 150-250mm diameter (per linear meter of piles) in normal soil | 25-35 |
| 11-Bored piles, using hydraulic piling machinery, 500-600mm diameter (per linear meter of piles) in normal soil | 40-50 |
| Excluding VAT | |
| Last updated February 2019 | |