SITE WORKS
Description USD
I- Excavation & Clearing  
1- General excavation of normal soil including hauling away and dumping of material to municipality-approved pits (in m³) 8-9
2- General excavation of rock including hauling away and dumping of material to municipality-approved pits using explosives (not exceeding 1 m depth) (in m³) 10-11
3-Trench excavation for Sewage network, Piping depth between ( 0 - 2 m ), width between ( 0.6 - 1 m) 12-13
4- Clearing of site in soft to medium hard ground including hauling away and dumping of material to municipality-approved pits (in m²) 9-10
   
II- Filling & Backfilling (all in m³)  
5- Backfilling with approved excavated materials stored on site around foundations including watering and compaction (in layers not exceeding 300mm depth) 8-9
   
III- Shoring (all in m²)  
6- Diaphragm wall for watertight excavation including excavation, tie-back system and dewatering, 600mm thick 450-500
7- Ditto, 800mm thick 500-550
8-Interspaced pile wall with shotcrete for dry excavation including excavation and tie-back system 350-400
9-Secant pile wall for watertight excavation including excavation, tie-back system and dewatering 425-475
   
IV- Foundation Piling (Drilling only)  
10-Micro piles, using hydraulic piling machinery, 150-250mm diameter (per linear meter of piles) in normal soil 25-35
11-Bored piles, using hydraulic piling machinery, 500-600mm diameter (per linear meter of piles) in normal soil 40-50
   
Excluding VAT
Last updated February 2019